The motor sizing method is unchanged. One section is new. It's a flat prohibition, and it's already in the printed book.

Quiz yourself: did this section move?

On this page
  1. The one new section, and where it came from
  2. The method that did not change, and still catches people
  3. Where the rounding rule reverses
  4. The group rule that gets over-applied
  5. Reading Article 430 without getting lost
  6. What this page cites

The one new section, and where it came from

A ground-fault circuit interrupter, or a special purpose ground-fault circuit interrupter, shall not be installed between the output terminals of power conversion equipment and the motor (NEC 430.132).

That is the whole section. It is a prohibition about a location, with no calculation in it, and it applies to the run between a drive output and the machine it turns.

It reached the book by tentative interim amendment. NFPA issued TIA 26-3 against the 2026 edition on 20 August 2025 with an effective date of 9 September 2025, and the amendment sheet records that the text was approved for incorporation into the document before printing.

So there is nothing to chase here. If you are holding a 2026 code book, 430.132 is printed in it. Checking the current amendment list for NFPA 70 is still worth doing before you rely on any section for real work, but you will not find this one waiting there.

Texas adopted the 2026 edition effective September 1, 2026 under 16 TAC 73.100, which is the date the section started deciding inspections here.

The method that did not change, and still catches people

Article 430 continues to use two different currents for two different jobs, and this is where most motor errors start (NEC 430.6).

They are usually close and almost never equal. Overload protection works from the nameplate, and the conductors and their short-circuit protection work from the table.

The reason is not arbitrary. Overload protection is watching one specific motor, so it reads that motor. Short-circuit protection has to survive inrush, which is a property of the motor class, so the code standardizes it with a table.

Where the rounding rule reverses

On a general conductor, rounding the protective device up to the next standard size is permitted only when three conditions are met, one of which caps the selected rating at 800 amperes (NEC 240.4(B)).

On a motor branch circuit, rounding up is the expected path. The percentage from the branch-device table rarely lands on a standard rating and the code anticipates taking the next one (NEC 430.52).

Two rules that both say next higher standard size, pointing in different directions, used in the same problem. Knowing which article you are standing in is the whole thing.

The group rule that gets over-applied

For a feeder serving several motors, only one motor gets the 125 percent (NEC 430.24).

The sum has four parts. The highest rated motor is taken at 125 percent. Every other motor in the group is taken at its full-load current with no uplift. The non-motor load is added at its full value if it is noncontinuous, and at 125 percent if it is continuous.

Applying 125 percent to every motor produces a conductor that is oversized and a number that is wrong. The margin exists to cover one motor starting while the rest run.

Highest rated is settled by the section itself, which points at 430.6(A)(1) for the figure. That is the table current, so the largest motor in the group is the one with the largest table current, whatever its horsepower. On a mixed single-phase and three-phase group those can be different motors.

Reading Article 430 without getting lost

Article 430 is long and its parts follow function, out of step with the order you work in, which is why it reads badly front to back.

Figure 430.1 at the front of the article maps which part answers which question. It is the fastest navigation aid in the code and most people never open it.

Put your tab on that figure. It will save more time than any other single tab in the book.

Before the exam, or the inspection

See where 50 of the 2023 numbers went

Fifty 2023 numbers, each with where the rule sits now, what took over the old number, and the document it was read in. $29 once, and ten of them are free in the quiz first.

37 of the 50 were read in the printed 2026 book, 12 in NFPA panel drafts, and 1 is not settled. Each row says which, and corrections go in the public log.

What this page cites

An email when a Texas exam rule or fee changes

TDLR writes Texas exam rules and fees into 16 TAC Chapter 73, which also sets the code edition, and PSI's candidate bulletin carries the exam details. If either changes an exam rule, a fee or a code date, we send one short email about it, and the link at the bottom of every email takes you off the list.