Checked against primary sources 2026-08-24
Some rules in the book you are holding start on their own date
A rule can be printed, adopted and enforceable, and still not apply to you until a date years away. The book says so in the sentence, and it is easy to read past.
Quiz yourself: did this section move?
On this page
Why this exists at all
Some requirements depend on a product being listed, and on the listing standard and the manufacturers being ready. Writing the requirement now and starting it later gives the supply chain time to catch up.
The consequence for you is that the same paragraph can be both current code and not yet applicable, and only the last sentence tells you which.
What we have found so far
Already running
Three of the dates we found had already arrived. Texas adopted the 2026 edition effective September 1, 2026 under 16 TAC 73.100, after all three, so these reached Texas jobs already in force with no waiting period at all.
| Started | Where | What started |
|---|---|---|
| January 1, 2026 | 424.48 | Heating cables and cable sets installed in walls: a 4 foot height limit, with both GFCI and AFCI protection. |
| January 1, 2026 | 424.93(C) | The same height limit and the same two kinds of protection, for heating panels in walls. |
| January 1, 2026 | 555.35(E) | The listing requirement for the leakage current measurement device used at marinas. |
Still ahead
The rest sit in the over-1000-volt articles, the medium voltage cable article, the electrified truck parking article and the pool article, and they run to 2032.
| Starts | Where | What starts |
|---|---|---|
| January 1, 2029 | 245.2(A) | Listing of overcurrent protection for systems not over 15,000 volts. |
| January 1, 2029 | 495.2(A) | Listing of switchgear and industrial control assemblies not over 15,000 volts. |
| January 1, 2029 | 626.30(C) | Special purpose ground-fault circuit-interrupter protection for receptacles that supply transport refrigerated units at electrified truck parking spaces, on branch circuits rated more than 150 volts to ground and 100 amperes or less. |
| January 1, 2029 | 680.26(B)(2)(a), which Errata 70-26-2 renumbers 680.26(B)(2)(b) | Listing, for corrosion resistance and mechanical performance, of the copper grid or welded wire used in pool equipotential bonding where it is not fully embedded in concrete. |
| January 1, 2032 | 245.2(B) | The same listing duty for overcurrent protection over 15,000 volts and not over 52,000 volts. |
| January 1, 2032 | 495.2(B) | The same listing duty for assemblies over 15,000 volts and not over 52,000 volts. |
| January 1, 2032 | 315.2 | Listing of Type MV cable joints, cable terminations and connectors. |
The two over-1000-volt articles are built the same way. Each has a Listing Requirements section at .2, each splits it into (A) for equipment up to 15,000 volts and (B) for equipment above that and up to 52,000 volts, and each gives the upper band three more years than the lower one.
245.2 carries an exception worth knowing before you price anything: overcurrent protection that is integral to a listed assembly shall not be required to be listed on its own (NEC 245.2). The assembly's listing covers it.
How to read one of these when you meet it
The sentence pattern is consistent, and the useful part is where it sits: in every one we read, the effective-date clause comes at the end of the requirement, after the rule it delays.
That is why it gets read past. By the time you reach it you have already decided what the paragraph says.
If you are checking whether something applies today, read the whole subsection to the end before deciding. The delayed date is not going to be in the first line.
What the 2029 and 2032 dates mean for a Texas job
They are not a distant horizon. They are inside a normal working career, and the first of them is closer than the gap between the last two code editions.
They will probably not reach you through this book, though. The NEC has come out every three years, and Texas took the 2023 edition on September 1, 2023 and the 2026 edition on September 1, 2026. On that pattern, whatever Texas has adopted in January 2029 is unlikely to be the book on your bench today.
The dates are still worth knowing, because they turn into a purchasing question long before they're an inspection question. Equipment bought now sits in service well past 2029, and the listing that is optional today is the one the next edition will expect.
The limits of this list
This list comes from reading the printed 2026 book on 12 November 2026 for every sentence that sets a later effective date. Delayed dates can be worded in more than one way, so treat the tables as the dates that reading found.
The section numbers here are the ones the printed 2026 book uses. Check the subsection in your own copy before you cite it to anyone.
It is also worth saying plainly that a delayed date in the national code says nothing about what a local authority requires. An authority having jurisdiction can be stricter, and several are.
Questions people ask
Which rules in the 2026 NEC have delayed effective dates?
Ten, listed in the two tables above with their section numbers. Three had already started before Texas adopted the edition, and seven are still ahead, running to 2032. Each one was confirmed in the printed 2026 book on 12 November 2026.
What starts on January 1, 2029?
Four of them. Listing of overcurrent protection for systems not over 15,000 volts at 245.2(A), listing of switchgear and industrial control assemblies not over 15,000 volts at 495.2(A), special purpose ground-fault circuit-interrupter protection for transport refrigerated unit receptacles at electrified truck parking spaces at 626.30(C), and listing of the copper grid or welded wire used in pool equipotential bonding where it is not fully embedded in concrete at 680.26(B)(2)(a), which Errata 70-26-2 renumbers 680.26(B)(2)(b).
What starts on January 1, 2032?
Three. Two are the upper voltage tier of the 2029 listing duties: 245.2(B) takes overcurrent protection over 15,000 volts and not over 52,000 volts, and 495.2(B) takes assemblies in the same band. The third is 315.2, the listing of Type MV cable joints, cable terminations and connectors.
Which delayed dates have already arrived?
Three, all dated January 1, 2026, which is before Texas took the edition on September 1, 2026. They are the wall height limit with ground-fault and arc-fault protection for heating cables at 424.48 and for heating panels at 424.93(C), and the listing of the leakage current measurement device used at marinas at 555.35(E). Those reached Texas jobs in force with no waiting period.
See where 50 of the 2023 numbers went
Fifty 2023 numbers, each with where the rule sits now, what took over the old number, and the document it was read in. $29 once, and ten of them are free in the quiz first.
37 of the 50 were read in the printed 2026 book, 12 in NFPA panel drafts, and 1 is not settled. Each row says which, and corrections go in the public log.
What this page cites
- NEC 245.2 Listing Requirements for overcurrent protection over 1000 volts. (A) not over 15,000 volts, effective January 1, 2029. (B) over 15,000 and not over 52,000 volts, effective January 1, 2032. Both carry the integral-assembly exception. Read in NFPA's code-making panel 9 second draft, 24 August 2026. source
- NEC 495.2 Listing Requirements for switchgear and industrial control assemblies over 1000 volts, with the same two dates. The same draft prints 495.3 as Reconditioned Equipment with no effective date, which is what settles where the 2032 date lives. source
- NEC 424.48 Installation of cables in walls, with the height limit and the protection requirements, effective January 1, 2026. Companion rule for heating panels at 424.93(C). source
- NEC 555.35(E) Leakage current measurement device for marinas, read in the printed 2026 edition, page 70-595. The listing requirement became effective January 1, 2026, and 555.35(D) is boat hoists. source
- NEC 626.30(C) Special purpose ground-fault circuit-interrupter protection for receptacles that supply transport refrigerated units, effective January 1, 2029. Read in the printed 2026 edition, page 70-633. 625.54, page 70-630, is ground-fault circuit-interrupter protection for personnel at electric vehicle charging receptacles and carries no date.
- NEC 315.2 Listing Requirements for Type MV cable, with the listing of joints, terminations and connectors effective January 1, 2032. Read in the printed 2026 edition, page 70-244.
- NEC 680.26(B)(2) Perimeter surfaces. The January 1, 2029 listing date for a grid not fully embedded in concrete sits in (a) in the printed 2026 edition, page 70-661, and NFPA Errata 70-26-2, issued October 16, 2025, moves that paragraph to a new 680.26(B)(2)(b).
- 16 TAC 73.100 The rule that brings the 2026 National Electrical Code into force in Texas on September 1, 2026. source